Refurbishment of Office Space - Paddington
Client - Cable & Wireless
Location - 7th Floor, The Point, Paddington
Size - 18,550 sq.ft
Project Value - £465,000
Nature of work - Refurbishment of existing office space removing cellular offices and creating an open plan working environment, increasing the desk capacity allowing C&W to relocate staff from other sites. All work was exercised with over 100 staff in-situ and completed in four phases over eight weeks, with minimum disruption to staff. The project also gave C&W opportunity to enhance the work environment and a brighter colour scheme.
The project included the following:
- New entrance reception with bespoke desk
- 12 new meeting rooms
- New Breakout area / coffee bar
- New catering kitchen for board meetings
- New Dry store
- New Reprographics room
- New corporate artwork and colour scheme
- New desking and breakout furniture
- Updating Exec office to provide more confidential environment
The following services were required to complete project:
- Overall Programme Management liaising with internal C&W staff and external Contractors.
- Interior Design
- Space planning and space utilisations
- Storage Survey
- Relocation management dealing with end-users and external removals contractor
- Project monitoring and reporting to C&W Property and Client Contact
- Client Representative Role for dealing C&W Legal team and Landlords Agent
- Project Documentation and Contract administration
- Furniture procurement & installation Project Management
- Cost Management and Budget Control
- Full Project Management ensuring the project was delivered on-time and within budget.