Worldwide House, Bracknell - Part 3 - Relocation Management
Client - Cable & Wireless
No of people: 600+
Duration: relocated over 2 consecutive weekends
Relocation Project Managers liaised with the Business Area Representatives to establish specific requirements, including decommision and re-installation of networks, printers, telephones to ensure business continuity.
Worked closely with Business Move Group (see useful links), to discuss client requirements, access to buildings, time frames, transportation, number of crew required, security passess, number of crates, labels including number of cable ties required! No detail was overlooked.
Phase 1 - approx 300 people over 1st weekend - 4 Directorate Groups - move started Friday evening and everyone was fully operational by Monday morning
Phase 2 - approx 310 people over 2nd weekend, all ready to start business on Monday morning
Completed successfully and on time.